Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • % Complete – 

    • Completed percentage is displayed as a slider bar and numerically.

    • The colour of the slider bar represents the colour of the project performance traffic light.

    • You can adjust the project percent complete using the slider and the %complete figure will change accordingly. Furthermore, you can also enter a percentage value and the slider bar will automatically change to represent that numeric value.

    • The ‘Status’ dropdown will automatically change as the percentage changes.

      • If “% Complete” is ‘0’, then “Status” is ‘Not Started’.

      • If “% Complete” is ‘100’, then “Status” is ‘Completed’.

      • If the “0 <% Complete <100”, then “Status” is ‘In Progress’.

      • You will not be able to make changes based on edit permissions.

  • Target –

    • Target will be non-editable and the value will be derived based on the following logic.

      • If the project progress is ‘Action Based Progress’ and the project is linked to an action, the target will be based on the action target.

      • If the project progress is ‘Action Based Progress’ and the project is NOT linked to an action, the target will be based on the calculation method defined.

      • If the project progress is ‘Project Based Progress’, the target will be based on the progress calculation method defined.

  • Status –

    • When the ‘Status’ dropdown is editable, ‘% Complete’ (slider bar and the numeric figure) will automatically change based on the ‘Status’ as given below.

      • If ‘Status’ is ‘Not Started’, then ‘% Complete’ is ‘0’.

      • If ‘Status’ is ‘Completed’, then ‘% Complete’ is ‘100’.

      • If the ‘Status’ is ‘Ongoing’, then ‘% Complete’ is blank.

      • If the ‘Status’ is ‘In Progress’, then ‘%Complete’ will be editable and the value should be “0 <value <100”.

      • If the status is  ‘Deferred’, then ‘% Complete’ will be editable editable.

  • Start Date/End Date – 

    • Project Start and End date will be editable/non-editable based on the external setting “Is Project Duration Based On Gantt”.

    • If “Is Project Duration Based on Gantt” is turned on: Start and End date will be non-editable. Project start and end dates will automatically adjust based on the earliest start and latest finish of the Gantt.

    • If “Is Project Duration Based on Gantt” is turned off: User will be allowed to edit the project start and end dates.

  • Baseline Start Date/ Baseline End Date – Displays the project Baseline Start Date.

  • Append Task Comment button - You can add task comments to the overall project comment by clicking on this button.

  • Project Comment – The project comment will not be editable when the project is linked to an action which is collaborative.

...