Please refer to the Common Icons when you are updating individual or multiple records.

Info
  • Setting the Status as ‘Not started’ or 'ongoing' will automatically set the percentage completed to 0%.

  • Setting the Status as ‘Complete’ will automatically set the percentage completed to 100%. When the status is set to complete, ‘Completed Date’ field will be enabled allowing you to enter the actual date of completion. This may be mandatory or optional depending on the configurations done by your Administrator.

  • You will not be able to modify the Completed percentage for ‘Not started’, ‘ongoing’ or ‘Completed’ Statuses. However, ‘IN PROGRESS’ or ‘DEFERRED’ statuses have a modifiable field for entering the completed percentage. This field may only have a number between 0 and 100.   

Info

Note: If a staff assigned for a Task is inactive, an inactive suffix will appear next to staff name.

...