EIS Risks tab would display all risks linked to the given hierarchy level. This area will be available only if you are using Integrated Risk Manager, along with Camms.Strategy®Strategy.

Clicking on a risk would take you to the page that contains details of the selected risk.

...

Field

Description

Risk Code

Risk code as displayed in Risk details area.

Risk Title

Title of the Risk. Clicking the hyperlink will direct you to the Risk details screen.

Risk Type

The type of the risk; i.e. Strategic, operational or project.

Responsible personPerson

The primary responsible person of the risk.

Current Assessment

The latest assessment stage of the risk. This could be initial, revised or future.

Initial Rating

The initial assessment rating is displayed here (CAMMS default image should be displayed if IRM administrator has not included an custom image via Risk Settings area).

Revised Rating

Revised assessment rating is displayed here (CAMMS default image should be displayed if IRM administrator has not included a custom image via Risk Settings area).  Instances where revised assessment is not initiated then rating will be displayed as N/A.

Future Rating

Future assessment rating is displayed here (CAMMS default image should be displayed if IRM administrator has not included a custom image via Risk Settings area).  Instances where Future assessment is not initiated then rating will be displayed as N/A.

Next Review Date

Next review date indicated in the Risk Review screen will be displayed here. The overdue indicator is displayed next to the date if the risk is overdue.

Email

Displays the email control.

...