Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

This article contains:

Table of Contents
minLevel1
maxLevel7
stylenone

1. Overview

The following rules apply to the task sorting within the task grid.

...

Info

Note: If the action is linked to a Camms.Project® Project, and that particular project already has tasks, then the tasks will appear in the order as they appear within the task planning object/schedule within cammsproject®.

This ordering applies to all sub-tasks as well.

2. Related Plans

Related plans are any internal and external plans normally found in an organisation such as the Human Resources Plan, Occupational Health and Safety Plan, Risk Management Plan and others.

...