This article contains:

Table of Contents
minLevel1
maxLevel7
stylenone

1. Overview

This outlines the steps to be followed in order to import the project schedule (Gantt chart) to Microsoft Project, edit projects tasks within Microsoft Project and export the changes back to the Camms.Project.

2. Prerequisites

Microsoft Project Professional software should be installed in your machine.

Info

Note: This functionality is available only for Forms Authenticated and Windows Authenticated clients.

3. Installation Process

  • STEP 1: Open any project and navigate to task planning (Gantt) area. Then click on the Download MS Project Add-In button placed above the Gantt.

Image Added
  • STEP 2: Once you click on the icon, a pop-up will be displayed for you to download and install MS Project Add-In. Click on Download link in the pop-up in order to commence the installation.

Your configuration details will appear in the pop-up as well. These details are specific to your environment, and you will need these details to configure the add-in in MS project after installation.

Image Added
  • STEP 3: 'Download’ the MS Project Add-In Installer.exe to download the set-up file.

Image Added
  • STEP 4: Once the download is completed, click on Open File.

Image Added
  • STEP 5: Next a pop-up will appear to extract MS Project Add-In files. Browse for a relevant location and then click on Install button.

Image Added
  • STEP 6: Next, navigate to the ‘Destination Folder’ mentioned above and extract the ZIP files. Then open the folder and click on CAMMS.ProjectAddinSetup.

Image Added
  • STEP 7: Once you click, the setup wizard will be initiated. Click Next to proceed with the installation.

Image Added
  • STEP 8: Browse for the relevant folder to save the set-up files.

Image Added
  • STEP 9: Click on Disk Cost button to view a list of drives available for you to select to install the project add-in. It also includes each drive’s available and required disk spaces.

Image Added

Once you select the folder, click on Next.

  • STEP 10: Click Next again to confirm the installation.

Image Added
  • STEP 11: Once the add-in is installed successfully, the installation message will be displayed. You can close the dialog-box. 

Image Added

4. Configuring the Project Add-In

  • STEP 1: Open MS Project. Please note that when you open the application, the following message will be displayed. Click on Install.

Image Added
  • STEP 2:  Select ‘Blank Project’ and navigate to ‘CAMMS plug-in’.

Image Added
  • STEP 3: Click on Settings button and the ‘Configuration’ side pane will appear.

Image Added
  • STEP 4: Add the relevant credentials (Please Refer Section 1 – Step 02) in the ‘Configurations’ area to set up the Add-In.

Info

Note: Authentication mode will be set to ‘Manual’ by default. If you are logged in through windows authentication, then you can select ‘Windows’ option and specify the ‘Organisation’. Backup File Settings: The files will be saved to the location specified in ‘Default backup location’.

  • STEP 5: Once you enter relevant details, click Test to test and set-up.

Image Added

If any configuration details are missing or incorrect, an error message will be displayed:

Warning Message for Missing Credentials

Image Added

Warning Message for Incorrect Credentials

Image Added

If the ‘Test’ is successful, the following message will be displayed:

Image Added
  • STEP 6: Click on Save button to save the configuration details.

Image Added

5. Opening & Editing Projects in Microsoft Project

  • STEP 1: Once the above configurations are successfully saved, the Open button in the top left hand side corner will be activated. Click on this button and you will be presented with a small window to search for the desired project.

  • STEP 2: You can search and locate the relevant project by using the filters given within ‘Select Project’ pop-up.

    • Name: Search by the project name.

    • Code: Search by the project code.

    • Owner: Search by the project owner.

    • Start and End Date: Search by your projects start and end dates.

  • STEP 3: Click Search and the relevant projects will be displayed.

  • STEP 4: Once the required projects are filtered, select the relevant project and click on the Open button to open the task plan within MS Project. MS Project will open the task plan which is in current phase of the project workflow. The project will be opened in ‘View Only’ mode if you click the Pen button without selecting the Edit Project option.

Given below are the list of default fields in MS project and their corresponding Camms.Project fields:

Microsoft Project Field Name

Corresponding Camms.Project Field Name

Task Name

Task

Duration

Duration

Start

Start Date

Finish

End Date

% Complete

Progress %

My Status (Outline Code 2)

Status

Predecessors

Predecessors

Resource Name

Responsible Person

  • STEP 5: Projects which are opened in 'View Only' option should be first 'Checked Out' in order to save changes to the Camms Server.  Click on the Checkout button.
    You will be prompted with a ‘Save Confirmation’ message and click Yes to proceed.

  • STEP 6: Make any change to the Task Plan in MS Project. You may copy and paste previous MS Project sheets into this checked out project sheet in order to import it back into Camms.

  • STEP 7: Once you have completed all changes, in order to import the Task Plan back to Camms.Project, click on Check In button in the top panel.

    Ensure that all mandatory fields are completed. Otherwise, an error message will be displayed.

    Mandatory columns include Task Name/Start/Finish Date/% complete /Resource Name.

Image Added

A message will indicate to you once the changes are successfully saved to the Camms Server.

  • STEP 8: The projects which are already Checked Out by one user cannot be edited in MS Project by another user. The 'Edit Project' tick box will be automatically disabled for editing. This will also show the person who checked-out the project along with the date.

Image Added

Once the project is checked-out in Microsoft Project, ‘Add, Indent/Outdent, Delete and Move Up/Move Down’ options will be disabled from the Camms.Project Gantt.

The Administrator will have to discard check-out from Camms server in order for another user to edit or else the project will need to be 'Checked In' again.

6. Download Log

Click on Download Log to view the error log:

Image AddedImage Added
UG Footer 2024-20240103-072111.pngImage Added