The projects can be differentiated as per 'Open', 'Close' and 'Upcoming'.
When the close project sign off object is approved, then the project is considered
...
Closed
...
.
When the close project sign off object is not approved/not submitted/pending approval,
If the project start date is greater than the current financial period, then the project is considered
...
Upcoming
...
.
If the project start date is within the current financial period, then the project is considered
...
Open
...
.
Info |
---|
Example 1: Current financial period: 1/06/2016 to 30/06/2017 Project start date: 08/08/2017 Close project sign off status: Not Submitted View date: 30/08/2016 Project status: Upcoming Example 2: Current financial period: 1/06/2016 to 30/06/2017 Project start date 15/02/2017 Close project sign off status: Not Submitted View date: 30/08/2016 Project status: Open |