The Task Update Object consists of one mandatory tab titled Task Update.
This object
Can be added multiple times within a workflow.
This is an independent and incremental object. Hence, the changes made to one instance will be reflected in all subsequent instances. However, the changes will not be reflected in the previous instances.
Can be renamed.
Prerequisites and Dependencies
If the project is linked to an action/task, any changes will be reflected in interplan and vice-versa.
Task Update
Field Name | Field Type | Default Display Name | Default Help Text | Default Settings | ||
---|---|---|---|---|---|---|
Field Enable | Field Visible | Field Compulsory | ||||
Timeframe Actual | Date display | Forecast/Actual: | Show Actual times | ALWAYS DISABLED | configurable | NEVER MANDATORY - |
TimeframeBaseline | Date display | Baseline: | Show Baseline times | ALWAYS DISABLED | configurable | NEVER MANDATORY - |
BaselineButton | Button | N/A | Baseline the current | configurable | configurable | configurable |