MQU – My Actions – Progress Threshold
This article contains: |
1. Progress Threshold |
You can define progress thresholds using this option. This is currently used for defining the thresholds for Action Traffic Lights. For more information on how the Action Progress is calculated, please refer the Action Progress Calculation section below.
STEP 1: Go to Administration > Camms.Strategy Configuration > Action Progress Threshold.
STEP 2: Specify ‘On track’ and ‘Off Track’ figures and click the save icon.
Business Rule
Action Performance >= On Track value = On Track → Green
Action Performance < Off Track value = Off Track → Red
Off Track value <= Action Performance < On Track value = Monitoring → Amber
Action Performance = Percent Complete / Period Target Value x 100
1.2 Action Progress Calculation
If the action has no tasks/ has task but weightings are not defined, then action progress will be as per the ‘Percent Complete’ set for that particular action.
However, if the action has tasks defined and weightings are given then action progress will be calculated as follows:
Task | Complete | Weightings |
---|---|---|
Task1 | 65 | 25 |
Task2 | 50 | 75 |
Action Percent Complete = [(65*25) + (50*75)] / 100
Note that, if an action has targets defined, then those targets will not be considered when calculating action progress.
1.2.1 Action Progress Traffic Light Indicator
Action progress traffic light will display the following indication based on the ‘Action Progress Threshold’ configured within the configuration area.
On Track - GREEN
Monitor - AMBER
Off Track - RED
Action Progress Traffic Light Indicator will display a blank traffic light in following instances
For Ongoing Actions where the action progress values are not specified in the system by default.
Actions for which Target values have not been set within Action detail area.