Progress Calculation

Within progress calculation, you can define the project progress calculation option and progress thresholds that will be used throughout the system. 

...

 = (16.67/51) *100

 = 32.68%

Progress Threshold Setting
STEP 1: Specify ‘On track’ and ‘Off Track’ figures and click the "Save" icon.

The progress threshold defined here will be synchronised with the ‘Action Progress Threshold’ in planning area and vise versa.

Info

Business Rule

Project/action Progress >= On Track value = On Track = Green.

Project/action Progress <= Off Track value = Off Track = Red.

...