...
3. The Risk Title in the grid is hyperlinked. Click on the title and you will be navigated directly to Current Risk Assessment of the respective Risk within Risk Assessment object in Project Area.
...
Edit Risk Details
...
Inline Quick Update will display below information for each risk:
Risk Code – Displays the risk code for the risk.
Title – Displays the title for the risk. Click on this link to navigate to the current risk assessment screen of the respective risk within the risk assessment object in the project area.
...
Performance = (Actual Percent Complete / Target Percent Complete) * 100.
Info |
---|
Notes:
|
...
On Track: >= 90
Off Track: < 70
Monitor: Less than 90 and greater than or equal to 70 .
You can change the threshold values under the Progress Calculation page, accessed under, Framework > Project Settings > Progress Calculation.
...