System defaults to 'action based progress'.

Info

When 'Action based progress' is selected as default, in an instance where a project is not linked to an action the progress will be calculated using the project based calculation.

STEP 2: Select a Project Based Progress Calculation Method that would be used to calculate project based progress throughout the system.

...

 =  [<17/7/ to 26/9> / <17/7 to 3/12>]*100

 =  [51/100] * 100

 = 51%

Auto Achievement Progress Calculation Method

...

T3: [(10*100)/100] = 10

Sum of task days = 20

Actual = [# Task Days Completed/ # Total Task Days Scheduled] * 100

= [20/120] *100

= 16.67%

Performance = (Actual/Target) *100

...