Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Within progress calculation, you can define the project progress calculation option and progress thresholds that will be used throughout the system. 

...

Project progress calculation Options

Here you can define the calculation method for project progress that would be used throughout the system.

...

Refer Project Progress Calculation below, to see examples.

Project Progress Calculations

Example:

Time now = 26/9/12

Current baseline = Proposed (phase 2)
Task schedule is as follows:

Task

Scheduled Duration

Start Date

Finish Date

% complete

Task 1

100

17/07/2012

03/12/2012

0

Task 2

10

23/07/2012

03/08/2012

100

Task 3

10

30/07/2012

10/08/2012

100

Target = [ # Working days from current baseline start to Now/# Working days from current baseline start to finish]  *100

 =  [<17/7/ to 26/9> / <17/7 to 3/12>]*100

 =  [51/100] * 100

 = 51%

Auto Achievement Progress Calculation Method

Actual = [ Working days from Actual start date to Now/ # Working days from forecast start to finish] * 100  

 = [<17/7/ to 26/9>/ <17/7 to 3/12>] * 100

 = [51/100] * 100

 = 51%

Performance = (Target/Actual) *100

   = (51/51) *100

   = 100%

Total Duration Calculation Method

Task Days complete = Sum [ (# Days for each task *% Complete)/100]

T1 : [(100*0)/100] = 0

T2: [(10*100)/100] = 10

T3: [(10*100)/100] = 10

Sum of task days = 20

Actual = [# Task Days Completed/ # Total Task Days Scheduled] * 100

= [20/120] *100

= 16.67%

Performance = (Actual/Target) *100

 = (16.67/51) *100

 = 32.68%

Progress Threshold Setting

STEP 1: Specify ‘On track’ and ‘Off Track’ figures and click the "Save" icon.

The progress threshold defined here will be synchronised with the ‘Action Progress Threshold’ in planning area and vise versa.

Info

Business Rule

Project/action Progress >= On Track value = On Track = Green

Project/action Progress <= Off Track value = Off Track = Red

...