This area allows you to define a consequence reference table. The consequence reference table is meant to assist users in choosing a consequence level for risks by illustrating the description of Consequence (for if the risk were to occur) against each Risk Category defined. 

STEP 1: Click ‘Consequence Table'

...

STEP 2: Select the 'Project Risk' from the ‘select risk type’ dropdown.

...

STEP 3:Simply click inside each cell and type in any text as needed.

Click on the ‘Maximise’ button in order to maximise the screen for data input:

Image Added

...

STEP 4:Click the Save  icon to save the details.

Image Added

This will appear in the assessment areas as follows when assessing the criteria:

...

Tip

Tip: Based on the settings you have enabled, one or more Impact ratings can be selected and saved from here.

...