Actions – Risk

The Risk tab allows you to manage risks associated with an action.

image-20240828-055736.png
Figure 1.1
  • STEP 1: To manage Project risks related to an action, click the Risk tab.

  • STEP 2: Enter the Risk Code in the provided field. The Risk Code can be configured via Risk Settings > Risk Code and is generated based on the settings configured there. The following sequence types are available:

    • None: Users can manually enter a Risk Code.

    • Strict Sequential Numbering: The Risk Code is generated automatically and cannot be edited by the user.

    • Editable Sequential Numbering: A Risk Code is generated, but the user can modify it if needed.

Note: Based on the selected Risk Code configuration, the behavior will be reflected in the Risk tab.

  • STEP 3: Enter the Risk title in the Issue Risk field.

  • STEP 4: Select the appropriate Responsible Officer from the dropdown menu.

  • STEP 5: Click Add to save the risk details for the action.


<< Back to main section
Actions

 

UG Footer 2024-20240103-072111.png