Risk Settings – Multiple Consequences

This settings page enables you to define how multiple consequences are handled during a risk assessment. When the setting is ON, you can select multiple consequences for a single risk scenario. The overall consequence rating will then be determined based on your chosen method, either by using the maximum (MAX) consequence rating or the average (AVG) consequence rating. This setting ensures a comprehensive and accurate evaluation of potential outcomes, enhancing the robustness of your risk assessment process.

Note: "Multiple Consequences" is a one-time configuration. If you require any changes afterward, please contact Camms Support for assistance.

image-20240624-103547.png
Figure 1.1
  • STEP 1: Enabling Multiple Consequences Navigate to Framework > Risk Settings.

  • STEP 2: Click on Multiple Consequences to open the settings page, Toggle the Enable Multiple Consequences button ON.

Note: If you have only View permissions, the toggle, dropdown, and Save button will be disabled.

Once the toggle is ON, the Consequence Type Selection dropdown will be enabled.

  • STEP 3: Choose the Consequence Type:

    • Max: Selects the highest value of all selected consequences.

    • Average: Calculates the average value of all selected consequences by dividing the sum of all selected consequence values by the number of consequences selected.

  • STEP 4: To configure the Consequence fields within Risk Setting, Navigate to Mega Menu > Administration > Risk Settings > Criteria > Criteria Configuration tab.

image-20240813-105910.png
Figure 1.2
  • STEP 5: Select ‘Consequence’ from the ‘Risk Criteria Name’ dropdown, Click Add New to add new Risk Criteria Rating types. Fill in all mandatory fields.

Note: Use the Edit and Delete buttons to modify or remove Risk Criteria Rating types as needed

  • STEP 4: Click the Save button at the top to save details.