This area allows you to define additional performance thresholds for KPIs and KRIs beyond the standard three-tier system (On Track, Monitor, Off Track). You can configure up to five customised thresholds aligned to organisational needs.

Note: Performance thresholds for Scorecards will be based on the performance thresholds configured within this area.

  • STEP 1: Contact Camms Support to enable the internal setting for multiple performance statuses.

Once enabled, a new section titled KPI Performance Threshold will appear under Administration > Configuration.

image-20250701-095914.png
Figure 1.1
  • STEP 2: Set up access permissions for the KPI Performance Threshold page.

    • Clients on a static database with Administrator permissions will have direct access to this page.

    • Clients using a flexible hierarchy must assign access via the Role Management area by granting either View or Edit permissions, as required.

image-20250701-100558.png
Figure 1.2
  • STEP 3: By default, three thresholds titled On Track, Monitor, and Off Track will be displayed with their respective colours.

Click the Add New button to define more thresholds. Titles, colours, images, and display order can be configured. A maximum of five performance thresholds can be defined.

image-20250701-100614.png
Figure 1.3
image-20250701-100656.png
Figure 1.4

A visual representation will be shown for each calculation method based on the configured thresholds.

image-20250701-100708.png
Figure 1.5
  • STEP 4: Click Save once the configuration is complete.

The system will process KPI and Scorecard data for five financial years, including the current year.

You can choose to process data immediately or after office hours. Processing after hours is recommended to reduce system performance impact.

Note: The performance threshold configuration page will be disabled while data is being processed. Changes made within KPI components during this time may not be saved or could disrupt the process.

Once you save the performance threshold configurations, these settings will also apply to other areas of the system.

1.1 Strategy Map Configuration

When configured to display the overall performance of a hierarchy node by average, the number of variance fields will vary based on the number of configured thresholds.

Calculation Method

3 Performance Thresholds

4 Performance Thresholds

5 Performance Thresholds

Calculation Method

3 Performance Thresholds

4 Performance Thresholds

5 Performance Thresholds

Number of Variance Fields

1

2

3

image-20250701-101240.png
Figure 1.1.1

When configured to display by count, a dropdown labelled Overall Status Tie Resolution will be available. This allows administrators to select the preferred performance threshold to display in the case of a tie. By default, the higher performance threshold will be shown.

image-20250701-101406.png
Figure 1.1.2

1.2 KPI Target/Actual Tab

KPIs using the Goal Post calculation method will support all configured performance thresholds.

The number of variance fields will vary depending on the number of thresholds configured.

Calculation Method

3 Thresholds

4 Thresholds

5 Thresholds

Calculation Method

3 Thresholds

4 Thresholds

5 Thresholds

More is Better

1 variance field

2 variance fields

3 variance fields

Less is Better

1 variance field

2 variance fields

3 variance fields

Goal Post

2 variance fields

3 variance fields

4 variance fields

image-20250701-103358.png
Figure 1.2.1

1.3 Scorecards

The number of variance fields in Scorecards will vary based on the number of configured performance thresholds.

Calculation Method

3 Thresholds

4 Thresholds

5 Thresholds

Calculation Method

3 Thresholds

4 Thresholds

5 Thresholds

Number of Variance Fields

1

2

3

image-20250701-103519.png
Figure 1.3.1

1.4 KPI Graph

The KPI graph will display upper and lower boundaries based on the number of configured thresholds.

Calculation Method

3 Thresholds

4 Thresholds

5 Thresholds

Calculation Method

3 Thresholds

4 Thresholds

5 Thresholds

More is Better

1 lower boundary

2 lower boundaries

3 lower boundaries

Less is Better

1 upper boundary

2 upper boundaries

3 upper boundaries

Goal Post

2 upper and 2 lower boundaries

3 upper and 3 lower boundaries

4 upper and 4 lower boundaries

image-20250701-103630.png
Figure 1.4.1

1.5 Email Notifications

KPI performance-based email triggers will reflect the configured thresholds, allowing emails to be triggered for each performance level.

image-20250701-103731.png
Figure 1.5.1

1.6 Display Areas

KPI and Scorecard performance will be shown based on the configuration. The respective colour and title will be displayed across areas such as EIS and Strategy Map.

image-20250701-103817.png
Figure 1.6.1

1.7 Performance Calculation

Performance is calculated in two steps.

  • STEP 1: Performance Value Calculation

Calculation Method

Logic

Calculation Method

Logic

More is Better

If Target = 0 and Actual ≥ 0 then 100, else 0. Otherwise Actual divided by Target.

Less is Better

If Target = 0 and Actual ≤ 0 then 100, else 0. If Target > 0 then 1 minus (Actual divided by Target) plus 1. Otherwise Actual divided by Target.

Goal Post

If Actual is between LB1 and UB1 then 100. If Actual is less than LB1 then (Actual divided by Target) × 100. If Actual is more than UB1 then (Target minus (Actual minus Target)) divided by Target × 100.

LB1 = Target minus ((Target × Variance) ÷ 100)
UB1 = Target plus ((Target × Variance) ÷ 100)