Strategy Configuration – Action Progress Threshold

You can define progress thresholds (on track figure and off track figures) using this option. This is currently used for defining the thresholds for Action Traffic Lights. For more information on how the Action Progress is calculated please refer to the Action Progress Calculation article.

  • STEP 1: Go to Administration > Configuration> Action Progress Threshold.

Figure 1.1
  • STEP 2: Specify ‘On track’ and ‘Off Track’ figures and click the save icon.

Business Rule

Action Performance >= On Track value = On Track → Green

Action Performance < Off Track value = Off Track → Red

Off Track value <= Action Performance < On Track value = Monitoring → Amber

Action Performance = Percent Complete / Period Target Value x 100


<< Back to main section
Configuration

 

UG Footer 2024-20240103-072111.png